Comrat bypass, Moldova

M3 Comrat bypass, km 0+000 – km 18+263, Moldova

Our project, was funded by the European Investment Bank (EIB) and tendered by Moldovan Highways, has brought great comfort to Comrat, the 3rd largest city where the M3 highway connecting the north and south of Moldova passes, and has reduced the number of accidents caused by traffic and brought road comfort to the highest levels. Within the scope of the project; The construction works of a total of 2x1 lane 28.19 km long road, including the construction of 6 bridges and 22 culverts, have been completed by our company.

Procurement
Construction
Moldovan State Highway Administration
Total Asphalt Road Length = 28.19 km
Earthwork = 1,435,959.60 m3
Sand Drainage Layer = 94,237.37 m3
Granular Base Course = 102,824.00 tons
Cold Recycle Base Course = 81,669.18 tons
Bituminous Hot Mix Asphalt = 107,634.51 tons
Concrete = 9,334.00 m3
Road Painting (marking) = 13,967.75 m2
Metal Guardrail = 20,041.60 m
New Jersey Barrier = 840.00 m
Precast Piling Works = 2,825.40 m
Bridges = 6 pcs
Intersection = 4 pcs